Preparation of the Wall Surface
The successful application, bonding and correct hardening of
hydraulic lime mortars, requires that the background should be
clean, free from vegetation, free of containments and reasonably dry
throughout the wall mass. The wall should be structurally sound and
the masonry and bedding mortars in good condition.Where natural weathering or incomplete repair works have previously
been carried out, new repair work will be required to
correct these defects. In masonry the natural weathering process can
result in the loss of small stones, known as pinnings, which are
traditionally placed into wide bed joints between larger stones,
where these are missing their replacement should be carried out with
any general repointing work which needs to be undertaken. (See
repointing).
Where walls are covered in vegetation, lichen or moss, these should
be removed, by use of cutting stems, treatment with biocides and
eventual cleaning down with brushes, any remaining biological growth
can retain water and may in time grow back through the new lime
coatings.
The application of various coats of hydraulic lime should not be
seen as remedial repair works to the masonry background, the
replacement of loose or defective mortar, replacing missing stone
pinnings, repairing damaged brickwork or stonework are distinct
separate operations and there eventual outcome should be to present
a reasonably flat and even surface, which is structurally sound and
clean ready for the rendering application.
Suction Control and Bonding
Before the application of any new lime coatings it is vitally
important to check the degree of suction within the background. Poor
or excessive suction can result in a weak bonding with the substrate
caused by rapid de-maturing of the newly applied render. This will
result in a weak and powdery interface which could lead to later
failure and separation.
In situations where suction needs to be controlled, wetting down
will be required. On dense blocks or near impervious masonry, simply
dampening the surface with a mist spray may be all that is required.
On very porous surfaces such as old brickwork considerable wetting
will be required. Wet the wall with a hose, working from the top of
the structure, downwards, this may need to be carried out the
previous day and several times on the day before rendering commences
depending on the substrate.
The objective of the suction control is to achieve a thoroughly damp
surface, but not wet, i.e., the surface must not have running or
standing water remaining on the masonry or brick, this could form a
barrier between the coating and substrate.
A certain amount of suction is required for lime mortars to adhere
and stiffen so the exact amount of wetting down is decided by the
plasterer’s experience.
Salt Contamination
Where new lime coatings are to be applied to masonry which is salt
contaminated, the masonry should be allowed to dry fully before
applying new renders. This will allow salt to be detected on the
masonry and mortar joint surfaces, if excessive salt is identified
clay or lime mortar poulticing may be required. Specialist advice
should be sought.
Salt contaminates should never be washed from the surface, as this
will result in the crystallized salt returning to a soluble state
and retreating back into the pores of the masonry or brick. Where
detected on the masonry surface, the salts should be brushed from
the surface and cleaned away from the structure.
Scud or Keying Coats – (See Harling)
Techniques or render application (2 or 3 coat work)
The techniques employed in the application of hydraulic lime
plasters should be to ensure a correct bonding with the background
while striving to minimise shrinkage and rapid drying. These
techniques should be followed throughout the plastering process.
Lime plastering is generally applied in 3 coats, but it is common to
find 2 coats or even single coat work in vernacular or early
structures. In 3 coat work the first coat on masonry or brickwork is
generally known as the scratch coat or render coat. This coat is
applied at a maximum thickness of 10mm and is applied by use of a
steel trowel or thrown onto the wall by use of a harling trowel and
then flattened in by the steel trowel.
When the coat has firmed up but has not gone hard, the plaster is
keyed or scratched up to produce a key for the following coats. The
keying up is carried out by use of a lath scratcher or similar
toothed instrument and care should be taken not to cut through the
plaster coat back to the background.
The keying up is generally in the shape of diamonds of approximately
30mm spacing. This coat should be allowed to harden for 72 hours
minimum before further coats of plaster are applied. Before applying
the second coat the first coat should be checked for shrinkage
cracks, and these should be filled with plaster before proceeding
with further coats. The first coat should be brushed down to remove
any dust, which may have blown onto the surface. The first coat
should then be damped down to ensure that the second coat is applied
to a damp but not wet surface.
This second coat is called the floating coat and is the coat, which
is straightened to ensure a flat and even surface, after this coat
has been straightened, the surface of this coat is scoured up with a
timber or polyurethane float.
Surface Finish
Where possible the texture of the finished surface should be left
slightly open or coarse, as this will allow better evaporation of
moisture from the surface, the finished work should not be closed or
“trowelled” up with a steel trowel.
Day-Joints
Where day joints are unavoidable they should be hidden wherever
possible behind down-pipe runs or over the shortest possible areas.
When working with Roundtower NHL2 or NHL3.5 mortars the reworking of
the joint is usually achievable the next day by lightly spraying the
surface with water and rubbing up the joint with a wooden or
polyurethane float, if this process proves difficult cut away
approximately 50mm of the previous days render, it is this perimeter
zone which is most open to the air and will therefore dry first.
Pages To Print | Sand Selection |
Mortar Mixing | Pointing
| External Rendering |
| Internal Plastering |
Harling/Roughcasting | Limewashing
| Limecrete | Aftercare
|
|